Slag of Electric Steelmaking Process Handling Complex 300 tph (Republic of Belarus, 2013)

Customer: OJSC "MetallProfPererabotka" 247210, Republic of Belarus, Gomel region., Zhlobin Str. Pervomaiskaya, d.41, pom.2A

September 2013

Brief description

Features of the complex

Raw materials: slag of electric steelmaking process (partial processing is fabricated)

Capacity: 300 tons per hour.

Fractionary composure of the finished products:

Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

Gallery