Slag Handling Complex
on Alchevsk metallurgical combine, Alchevsk, Ukraine
The first project of company AMCOM LLC
in Ukraine. Works under this project have been begun in
2000. In territory JSC "Alchevsky metallurgical
combine" it was planned to install a complex on processing
metallurgical slag, that considerably to reduce the areas
slag and to provide combine with necessary raw material for
metallurgical shops.
The equipment of company AMCOM LLC has arrived
to Ukraine in the autumn of 2000. In parallel with it there
was a preparation of a platform under installation and
constructions for processing finished goods.
The combine itself has acted as the general
contractor. Design works by institute "GiProMez" carried
out Kharkov.
The first operational experience in the market of
Ukraine has appeared very successful not only for company
AMCOM LLC, but also for Customer (Combine).
Less than for three months, installation and
adjustment of a complex have been finished. Solemn opening
a complex on processing metallurgical slag of Alchevsk
metallurgical combine on December, 20th, 2000 took place.
From the first for work behind work of a complex
experts of our company observed. All categories of
maintenance, including current and unforeseen repairs, were
carried out by employees of company AMCOM LLC.
Economic results of work of the enterprise have
surpassed all expectations. The complex has paid back less
than for a year. Following inquiries of the consumer, for
this time, parameters of quality of an end-product (a
breakage for shops of combine) have been improved.
Now company AMCOM LLC offers technological
complexes with an opportunity quickly to change, during
processing, the basic parameters of quality in a wide
range.